Walshaw Moor wind farm application delayed

Share this story

← More Borough News

The application for a 34-turbine wind farm on Walshaw Moor has been pushed back eight months, from November to July 2027. Calderdale Energy Park says it needs more time for surveys, assessments and design work, with updated plans expected in early 2027.

Last month, CIO highlighted 14 problems facing the proposal, from protected peatland and flooding to aviation safety.

The bigger question now is whether those problems can be solved at all. More time allows further work—but can a revised design overcome the fundamental objections to building on this site?